In order to upgrade the signalling and tracks, all lines through Oxford will be closed for nine days from Saturday 29 July through to Sunday 6 August. In addition, there will also be a number of overnight and one-day closures before and after the core works.

This will allow Network Rail install three new high-speed crossovers to the north of the station between Walton Well Road bridge and Aristotle Lane footbridge, as well as complete track and resignalling work.

For information about the rail replacement services that will operate during this time visit https://www.gwr.com/travel-information/travel-updates/planned-engineering/oxford or to find out more about our work https://www.networkrail.co.uk/running-the-railway/our-routes/western/oxfordshire/oxfordshire-signalling-and-track-upgrades/