Temporary Traffic Regulation Order – S14 Road Traffic Regulation Act 1984
Temporary Road Closure – at High Street, Stonesfield

A request has been received from Southern Gas Network for a temporary road closure to apply to a section of High Street, whilst essential gas works are carried out.

A Temporary Traffic Regulation Order (TTRO) is being made to implement the temporary closure and will operate from 24/10/2022.

The estimated duration of the works is 8 days.

(The maximum duration of a TTRO on a road is 18 months and on a footpath is 6 months, or until completion of the works, whichever is the earlier.)

Notice of intention to make the Order will be published in the local press.

A copy of the drawing showing the extent of the closure and also the alternative route for traffic is attached.

Further information regarding the works may be obtained by contacting Tammy Keir on tammy.keir@sgn.co.uk T 10601 / RMF

High Street Stonesfield T10601 .pdf