Temporary Traffic Regulation Order – S14 Road Traffic Regulation Act 1984
Temporary Road Closure at Stonesfield, Peaks Lane

A request has been received from MKJ Group Ltd for a temporary road closure to apply to a section of Peaks Lane whilst essential fibre optic cabling works are carried out.

A Temporary Traffic Regulation Order (TTRO) is being made to implement the temporary closure and will operate from 3 August 2021. The estimated completion of the works programme is 16 August 2021. This is a 24 hour per day closure.

(The maximum duration of a TTRO on a road is 18 months and on a footpath is 6 months, or until completion of the works, whichever is the earlier.)

Notice of intention to make the Order will be published in the local press.

Access will be maintained for emergency service vehicles and for those frontages within the closure area, subject to the progress of the works. Please note that access routes will depend on exactly where the works vehicles are at any time and may need to be negotiated with the gang on site as necessary.

A copy of the drawing showing the extent of the closure and also the alternative route for traffic is attached.

Further information regarding the works may be obtained by contacting Nicole Allen of MKJ Group Ltd on 01488 73393 or email nicole@mkjgroup.co.uk

T8745 / RAG

Regards,

Robert Graham

Officer
Network Management
Communities
Oxfordshire County Council
Email:    Robert.Graham2@oxfordshire.gov.uk

Notice of Order T8745 Stonesfield, Peaks Lane.pdf